WATER AND SEWER PIPELINE LAYING

OLYMPUS DIGITAL CAMERALAYING 160mm PE SEWER RISING MAIN.

Trench is excavated using a trenching machine, while the pea gravel surround is installed using a low ground pressure tracked gravel cart.

Trench is backfilled with blade that compacts the spoil into the trench,leaving a level surface.

We can carry out all works including supply and lay pipe, temporary fencing, topsoil strip and full reinstatement works.

 

 

OLYMPUS DIGITAL CAMERAWATER MAIN LAYING

Backfilling a 90mm MDPE water main crossing arable farmland. Trench cut using trenching machine, 175mm wide, 1.2 metres deep.

 

 

 

 

 

 

OLYMPUS DIGITAL CAMERATrench Cutting

Trencher cutting trench and laying the water pipe, which has been previously electrofusioned together.